The Ladyface Greenway Project will begin utility work on January 21, 2025, lasting about 4 months. The first phase, potholing, will take 2 weeks, followed by underground conduit installation. Temporary daytime lane closures may occur, but full road closures will be avoided. Flaggers will direct traffic to ensure safety. Efforts will be made to minimize disruptions, and updates will be provided if the schedule changes.
Details
- Activity: Utility Work – Temporary Daytime Lane Closures
- Start Date:January 21, 2025
- Duration: Periodically throughout next 4 months
- Typical Working Hours: 7:00 AM – 2:00 PM, MON to FRI
What To Expect
- Vehicle and Bike Lane Closures on Agoura Rd. & Cornell Rd.
- Share the Road with Bicyclists & Pedestrians Detours, Signage & Traffic Delays
- Temporary One Lane Roads, Follow Flagger Instructions
- Reduced Speed Limits
Please be aware that due to the dynamic nature of construction and potential weather delays, certain work activities may take longer than initially anticipated.